Consider recommendations regarding the Tajiguas Landfill Phase IIC Groundwater Protection System, County Project No. 828356, Third District, as follows:
a) Approve the Statement of Final Quantities for work performed and materials supplied for this project by the contractor, Papich Construction Co., Inc. (not a local vendor), in the amount of $3,132,628.23; and
b) Find, pursuant to California Environmental Quality Act (CEQA) Guidelines Section 15162, that no substantial changes are proposed, and no new information of substantial importance has come to light regarding environmental effects of the Phase IIC project. The Notice of Completion and Statement of Final Quantities implement the Phase IIC project which was analyzed in the Tajiguas Landfill Expansion Project EIR, 01-EIR-05, and Tajiguas Landfill Reconfiguration and Baron Ranch Restoration Project Subsequent EIR, 08-EIR-00000-00007, certified by the Board of Supervisors on August 13, 2002 and May 5, 2009 respectively.
|
Title
Consider recommendations regarding the Tajiguas Landfill Phase IIC Groundwater Protection System, County Project No. 828356, Third District, as follows:
a) Approve the Statement of Final Quantities for work performed and materials supplied for this project by the contractor, Papich Construction Co., Inc. (not a local vendor), in the amount of $3,132,628.23; and
b) Find, pursuant to California Environmental Quality Act (CEQA) Guidelines Section 15162, that no substantial changes are proposed, and no new information of substantial importance has come to light regarding environmental effects of the Phase IIC project. The Notice of Completion and Statement of Final Quantities implement the Phase IIC project which was analyzed in the Tajiguas Landfill Expansion Project EIR, 01-EIR-05, and Tajiguas Landfill Reconfiguration and Baron Ranch Restoration Project Subsequent EIR, 08-EIR-00000-00007, certified by the Board of Supervisors on August 13, 2002 and May 5, 2009 respectively.
|