Title: Consider recommendations regarding the construction of 2010/1011 Countywide Preventive Maintenance Application of Scrub Seal and Micro-Surfacing, County Project No. 820621, as follows: a) Approve the plans and specifications for the construction of 2010/2011 Countywide Preventive Maintenance Application of Scrub Seal and Micro-Surfacing; b) Award the Construction Contract in the amount of $3,218,326.50 to the lowest responsible bidder, Windsor Fuel Company, Inc (not a local vendor), P.O. Box 1029 Pittsburg, CA 94565-1029, subject to the provision of documents and certifications as set forth in the plans and specifications applicable to the project, as required under California Law; c) Approve and authorize the Chair to execute the Construction Contract, upon return of the Contractor’s executed contract documents, and the review and approval of the County Counsel, Auditor-Controller and Risk Manager or their authorized representatives; and d) Approve contingency funds in the amount...
Sponsors: PUBLIC WORKS DEPARTMENT
Attachments: 1. Board Letter 4/19/11, 2. Street List 4/19/11, 3. Construction Contract 4/19/11, 4. Continuance Memorandum 4/19/11, 5. Board Letter 5/17/11, 6. Street List 5/17/11, 7. Construction Contract 5/17/11

Title

Consider recommendations regarding the construction of 2010/1011 Countywide Preventive Maintenance Application of Scrub Seal and Micro-Surfacing, County Project No. 820621, as follows:

 

a) Approve the plans and specifications for the construction of 2010/2011 Countywide Preventive Maintenance Application of Scrub Seal and Micro-Surfacing;

 

b) Award the Construction Contract in the amount of $3,218,326.50 to the lowest responsible bidder, Windsor Fuel Company, Inc (not a local vendor), P.O. Box 1029 Pittsburg, CA 94565-1029, subject to the provision of documents and certifications as set forth in the plans and specifications applicable to the project, as required under California Law;

 

c) Approve and authorize the Chair to execute the Construction Contract, upon return of the Contractor’s executed contract documents, and the review and approval of the County Counsel, Auditor-Controller and Risk Manager or their authorized representatives; and

 

d) Approve contingency funds in the amount of $173,416.33 for the construction of 2010/2011 Countywide Preventive Maintenance Application of Scrub Seal and Micro-Surfacing.