File #: 14-00296    Version: 1
Type: Agenda Item Status: Passed
File created: In control: BOARD OF SUPERVISORS
On agenda: 4/15/2014 Final action: 4/15/2014
Title: HEARING - Consider recommendations regarding the Northern Branch Jail Project 8600-Update, Approval of Preliminary Staffing Plan and Operating Cost Analysis, Receive Local Vendor and Labor Outreach Plan, Third District, as follows: (EST. TIME: 2 HR.) a) Receive a presentation from the Sheriff and General Services on the status of Northern Branch Jail Project 8600; b) Approve the Preliminary Staffing Plan and Operating Cost Analysis from the Sheriff's Office for the Northern Branch Jail Project; c) Adopt a Resolution authorizing the Sheriff, or his designee, to submit to the Board of State and Community Corrections certain required documents pursuant to Title 15, Section 1750 of the California Code of Regulations, as provided in the Preliminary Staffing Plan, and the Operating Cost Analysis (AB900 - State Project A05-120); d) Direct staff to make all necessary future submissions to comply with the requirements of the State and the Board of State and Community Corrections r...
Sponsors: SHERIFF-CORONER OFFICE, GENERAL SERVICES DEPARTMENT
Attachments: 1. Board Letter, 2. Attachment A-1 - Preliminary Staffing Plan, 3. Attachment A-2 - Operating Cost Analysis, 4. Attachment C-Resolution 4-15-14-Signed, 5. Attachment D- AB900 Project Application Timetable, 6. Attachment E - NBAR Concept Submisson, 7. Attachment F- Operational Program Statement, 8. Attachment G - Local Vendor and Labor Outreach Plan, 9. Attachment H - Jail Staffing Assessment, 10. Public Comment - Santa Maria Valley Contractors Association, 11. Presentation
Title
HEARING - Consider recommendations regarding the Northern Branch Jail Project 8600-Update, Approval of Preliminary Staffing Plan and Operating Cost Analysis, Receive Local Vendor and Labor Outreach Plan, Third District, as follows: (EST. TIME: 2 HR.)

a) Receive a presentation from the Sheriff and General Services on the status of Northern Branch Jail Project 8600;

b) Approve the Preliminary Staffing Plan and Operating Cost Analysis from the Sheriff's Office for the Northern Branch Jail Project;

c) Adopt a Resolution authorizing the Sheriff, or his designee, to submit to the Board of State and Community Corrections certain required documents pursuant to Title 15, Section 1750 of the California Code of Regulations, as provided in the Preliminary Staffing Plan, and the Operating Cost Analysis (AB900 - State Project A05-120);

d) Direct staff to make all necessary future submissions to comply with the requirements of the State and the Board of State and Community Corrections requirements as it relates to the Northern Branch Jail project AB 900 Phase II Conditional Award;

e) Receive and file the Local Vendor and Labor Outreach Plan, as prepared by Kitchell/CEM. Inc.;

f) Consider whether to direct General Services staff to return to the Board with a presentation regarding utilizing Local Construction Workforce Agreements; and

g) After considering the Final Subsequent Environmental Impact Report (EIR) that the Board of Supervisors certified on March 11, 2008, and the Addendum to that EIR that the Board of Supervisors received and considered on December 6, 2011 and October 8, 2013, determine pursuant to 14 CCR ? 15162(a) that no subsequent EIR or Negative Declaration is required for this project because of the following: 1) No substantial changes are proposed in the project which require major revisions of the 2008 Final Subsequent EIR; 2) No substantial changes have occurred with respect to the circumstances under which the project is undert...