limited to existing highways and streets, sidewalks, gutters, bicycle and pedestrian
trails, and similar facilities. Find that this project is also an emergency repair project
and is exempt from the provisions of the CEQA pursuant to State CEQA Guidelines
Section 15269(d), as this project will fix or restore existing highway and roads
damaged by natural disasters and will be initiated within one (1) year of the damage
occurring. A Notice of Exemption was filed on this basis on January 7, 2026, and the
proposed action is within the scope of that Notice of Exemption; and
f) Approve Budget Revision Request No. 1696 to establish Fiscal Year 2026 - 2027
appropriations of $558,270.00 in Public Works Roads-Operations Fund (Fund 0015)
for Services and Supplies, funded by an operating transfer from the Roads-Capital
Maintenance Fund. Establish appropriations of $558,270.00 in the Public Works
Roads-Capital Maintenance Fund for Other Financing Uses funded by a release of
Restricted Purpose of Fund Balance.
A-28)
PUBLIC WORKS DEPARTMENT
Consider recommendations regarding Award of Contract for Maria Ygnacio Bike Path
Storm Repairs Project, County Project No. 25STM3-2N04; Second District, as follows:
(4/5 Vote Required)
a) Approve the Project Plans and Specifications, on file in the Public Works
Department Office, located at 123 E. Anapamu Street, Santa Barbara, CA 93101, for
the construction of the Maria Ygnacio Bike Path Storm Repairs Project; County Project
No. 25STM3-2N04;
b) Award the Construction Contract for the Maria Ygnacio Bike Path Storm Repairs
Project in the amount of $563,965.00 to the lowest responsible bidder, Matcon General
Engineering, Inc., 531 Magnolia Avenue, Corona, CA 92879, subject to the provisions
of documents and certifications, as set forth in the Specifications applicable to the
Project, as required under California law;
c) Approve and authorize the Chair to execute the Construction Contract, which has
been reviewed and approved by County Counsel, Auditor-Controller, and Risk
Manager, or their authorized representatives;
d) Authorize the Public Works Director, or designee, to approve change orders for the
Maria Ygnacio Bike Path Storm Repairs Project for a contingency amount up to
$44,898.00 plus an additional amount of up to $84,000.00 for supplemental work items,
for a total of not to exceed authorization amount of $692,863.00;
e) Find that the Maria Ygnacio Bike Path Storm Repairs Project is categorically exempt
from the provisions of the California Environmental Quality Act (CEQA) pursuant to 14
CCR section 15301(c) as the proposed project(s) consists of the operation, repair,
maintenance, or minor alteration of existing public or private structures, facilities,
mechanical equipment, or topographical features, involving negligible or no expansion
of use beyond that previously existing, including but not limited to existing highways and
streets, sidewalks, gutters, bicycle and pedestrian trails, and similar facilities. Find that
the project is also an emergency repair project and is exempt from the provisions of the