Title: Consider recommendations regarding Cachuma Reservoir Re-Roof, Project No. 8437A, General Services Project No. 8588, Construction Contract Amendments No. 5 and No. 6, Third District, as follows: (4/5 Vote Required). a) Approve and authorize the Chair to execute Amendment No. 5 to increase the amount of the Contract with Hanly General Engineering Corp. (“Hanly”) for the Cachuma Reservoir Re-Roof project in the amount of $9,698.00 upon return of Hanly’s execution of Amendment No. 5 and the review and approval of County Counsel, Auditor-Controller and Risk Manager or their authorized representatives for a total amended contract amount of $325,556.00; b) Find that in light of the need to expediently reduce moisture and rusting within the roof of the Cachuma Reservoir for the health, safety and welfare of the people and for the protection of the property and project, it is in the public interest to waive all applicable competitive bidding requirements and procedures for the installation of...
Sponsors: COMMUNITY SERVICES DEPARTMENT
Attachments: 1. Board Letter, 2. Attachment 1 - DRAFT_Amendment #5_8588, 3. Attachment 2 - DRAFT_Amendment #6_8588, 4. Final Executed Amendment No. 5, 5. Final Executed Amendment No. 6

Title

Consider recommendations regarding Cachuma Reservoir Re-Roof, Project No. 8437A, General Services Project No. 8588, Construction Contract Amendments No. 5 and No. 6, Third District, as follows: (4/5 Vote Required).

 

a) Approve and authorize the Chair to execute Amendment No. 5 to increase the amount of the Contract with Hanly General Engineering Corp. (“Hanly”) for the Cachuma Reservoir Re-Roof project in the amount of $9,698.00 upon return of Hanly’s execution of Amendment No. 5 and the review and approval of County Counsel, Auditor-Controller and Risk Manager or their authorized representatives for a total amended contract amount of $325,556.00;

 

b) Find that in light of the need to expediently reduce moisture and rusting within the roof of the Cachuma Reservoir for the health, safety and welfare of the people and for the protection of the property and project, it is in the public interest to waive all applicable competitive bidding requirements and procedures for the installation of gable vents and roof ventilation, which is additional work to be performed by Hanly under Amendment No. 6 to the Contract with Hanly;

 

c) Approve and authorize the Chair to execute Amendment No. 6 to increase the amount of the Contract with Hanly for the Cachuma Reservoir Re-Roof project in the amount of $22,256.00 upon return of Hanly’s executed Amendment No. 6 and the review and approval of County Counsel, Auditor-Controller and Risk Manager or their authorized representatives for a total amended contract amount of $347,812.00;

 

d) Re-authorize the Director of General Services or designee to approve change orders for a total amount not to exceed $19,708.00 for this Contract; and

 

e) Find that pursuant to the California Environmental Quality Act (CEQA) Guidelines Section 15162, no substantial changes are proposed, and no new information of substantial importance has come to light regarding environmental effects of the project or of the sufficiency or feasibility of mitigation measures, and therefore these actions are within the scope of the project covered by the Mitigated Negative Declaration 09NGD-00000-00024 and monitoring program approved and adopted by the Board for this project on April 19, 2011, and determine that therefore no new environmental document is required.