File #: 07-00805    Version: 1
Type: Agenda Item Status: Passed
File created: 8/10/2007 In control: BOARD OF SUPERVISORS
On agenda: 8/21/2007 Final action: 8/21/2007
Title: Consider recommendations regarding Hardinge Avenue Storm Damage Repairs (County Project No. 05STRM-1T19), First District, as follows: a) Accept the Notice of Completion for the work performed by the Contractor, Souza & Peterson Construction, Inc., (not a local vendor), P.O. Box 2057, Nipomo, CA 93444; and b) Review and approve the Statement of Final Quantities for work performed and materials supplied for this project by the Contractor in the amount of $251,347.87.
Sponsors: PUBLIC WORKS DEPARTMENT
Attachments: 1. Board Letter, 2. Statement of Final Quantities, 3. Notice of Completion
Title
Consider recommendations regarding Hardinge Avenue Storm Damage Repairs (County Project No. 05STRM-1T19), First District, as follows:
 
a) Accept the Notice of Completion for the work performed by the Contractor, Souza & Peterson Construction, Inc., (not a local vendor), P.O. Box 2057, Nipomo, CA 93444; and
 
b) Review and approve the Statement of Final Quantities for work performed and materials supplied for this project by the Contractor in the amount of $251,347.87.
Body
[Enter body here.]