File #: 01-00421    Version: 1
Type: Agenda Item Status: Passed
File created: 4/25/2001 In control: BOARD OF SUPERVISORS
On agenda: 2/20/2001 Final action: 2/20/2001
Title: Consider recommendations regarding the East Santa Maria Drainage Improvements Project (SM8202), Fifth District, as follows: a) Relieve the apparent lowest bidder Golden State Boring & Pipe Jacking, Inc. pursuant to Chapter 5 of the Public Contract Code of their bid submitted on January 30, 2001 for the project; b) Award and authorize the Chair to execute the agreement in the amount of $242,131 to the second apparent lowest responsible bidder A.J. Diani Construction Co., (a local vendor) subject to provision of documents and certification as set forth in the plans and specification applicable to the project and as required under California law; c) Approve a contingency fund in the amount of $24,213.10 for the above project.
Sponsors: BOARD OF DIRECTORS, FLOOD CONTROL AND WATER CONSER

Title

Consider recommendations regarding the East Santa Maria Drainage Improvements Project (SM8202), Fifth District, as follows:

 

a) Relieve the apparent lowest bidder Golden State Boring & Pipe Jacking, Inc. pursuant to Chapter 5 of the Public Contract Code of their bid submitted on January 30, 2001 for the project;

 

b) Award and authorize the Chair to execute the agreement in the amount of $242,131 to the second apparent lowest responsible bidder A.J. Diani Construction Co., (a local vendor) subject to provision of documents and certification as set forth in the plans and specification applicable to the project and as required under California law;

 

c) Approve a contingency fund in the amount of $24,213.10 for the above project.

 

Body

[Enter body here.]