File #: 11-00320    Version: 1
Type: Agenda Item Status: Passed
File created: 4/8/2011 In control: BOARD OF SUPERVISORS
On agenda: 4/19/2011 Final action: 4/19/2011
Title: Consider recommendations regarding the Lake Cachuma Fire Suppression Water Reservoir, Project No. 8717, Third District, as follows: a) Adopt the Final Mitigated Negative Declaration dated January 15, 2010 pursuant to the County’s California Environmental Quality Act (CEQA) guidelines for the Lake Cachuma Fire Suppression Water Supply Reservoir Improvements and Roof Replacement Projects for the Parks Department (Document available for review at General Services Department Office); b) Award a Fixed Price Construction Contract in the amount of $694,690.00 to the lowest responsible bidder, Brough Construction, Inc. (a local vendor) subject to the provisions of the documents and certifications as set forth in the plans and specifications applicable to the project and as required by California Law; c) Approve and authorize the Chair to execute the Construction Contract upon return of the Contractor’s executed contract documents, and the review and approval of County Counsel, Auditor-Cont...
Sponsors: GENERAL SERVICES DEPARTMENT
Attachments: 1. Board Letter, 2. Construction Contract

Title

Consider recommendations regarding the Lake Cachuma Fire Suppression Water Reservoir, Project No. 8717, Third District, as follows:

 

a) Adopt the Final Mitigated Negative Declaration dated January 15, 2010 pursuant to the County’s California Environmental Quality Act (CEQA) guidelines for the Lake Cachuma Fire Suppression Water Supply Reservoir Improvements and Roof Replacement Projects for the Parks Department (Document available for review at General Services Department Office);

 

b) Award a Fixed Price Construction Contract in the amount of $694,690.00 to the lowest responsible bidder, Brough Construction, Inc. (a local vendor) subject to the provisions of the documents and certifications as set forth in the plans and specifications applicable to the project and as required by California Law;

 

c) Approve and authorize the Chair to execute the Construction Contract upon return of the Contractor’s executed contract documents, and the review and approval of County Counsel, Auditor-Controller and Risk Manager or their authorized representatives; and

 

d) Authorize the Director of General Services or designee to approve change orders up to the limit specified in Public Contract Code Section 20142, or $42,788.00 for this Contract.