Title
Consider recommendations regarding the Jail All-Purpose (A/P) Room Conversion and Sheriff’s Headquarters Expansion Project No. 8682, Approval of Plans and Specifications, Amendment No. 2, CEQA Exemption, Authorization to Bid, Second District, as follows:
a) Approve the revised plans and specifications for the Jail All-Purpose (A/P) Room Conversion and Sheriff’s Headquarters Expansion Project No. 8682;
b) Approve and authorize the Chair to execute Amendment No. 2 to the Professional Services Agreement with Kruger Bensen Ziemer Architects (a local vendor) for the Sheriff’s Headquarters Expansion Project;
c) Approve the Categorical Exemption pursuant to the County’s California Environmental Quality Act (CEQA) guidelines for the Jail A/P Room Conversion Sheriff’s Headquarters Expansion, Project No. 8682; and
d) Authorize the Director of General Services to advertise for construction bids for the Jail A/P Room Conversion and Sheriff’s Headquarters Expansion, Project No. 8682.