Consider recommendations regarding the allocation of additional, unanticipated Federal Coastal Impact Assistance Program (CIAP) revenue, as follows:
a) Adopt a Resolution to allocate additional, unanticipated CIAP funds in the amount of $555,081.80 to the following Tier 1 and 2 projects:
i) $200,000.00 to fund engineering work for public access to Point Sal;
ii) $110,000.00 additional CIAP funds to removal of Arundo along the Santa Ynez River;
iii) $50,000.00 to fund engineering work for pedestrian beach access at Santa Claus Lane, thereby converting it from a Tier 2 to a Tier 1 project;
iv) $120,082.00 to fund improvements to the Walter Capps Park, thereby converting it from a Tier 2 to a Tier 1 project;
v) $25,000 to fund restoration work along Carpinteria Creek, thereby converting it from a Tier 1 to a Tier 2 project; and
vi) $50,000 to fund restoration work along Arroyo Burro Creek, thereby converting it from a Tier 1 to a Tier 2 project; and
b) Adopt a Resolution, approving a minor revision to the Agricultural Commissioner’s Santa Ynez River Restoration grant.