Title: Consider recommendations regarding the Via Rueda Interceptor Storm Drain Project Award, Second District, as follows: a) Award the construction contract for the Via Rueda Interceptor Storm Drain Project in the amount of $257,095.00 to the lowest responsible bidder, Tierra Contracting (a local vendor), subject to the provisions of documents and certifications, as set forth in the plans and specification applicable to the project and as required by law; b) Authorize the Chair to execute the construction contract upon return of the contractor's executed contract documents, and the review and approval of the County Counsel, Auditor-Controller, and Risk Manager or their authorized representatives; c) Approve a contingency in the amount of $25,354.75 for the above subject project; and d) Approve plans and specifications for the project.
Sponsors: BOARD OF DIRECTORS, FLOOD CONTROL AND WATER CONSER
Attachments: 1. Board Letter
Title
Consider recommendations regarding the Via Rueda Interceptor Storm Drain Project Award, Second District, as follows:
 
a) Award the construction contract for the Via Rueda Interceptor Storm Drain Project in the amount of $257,095.00 to the lowest responsible bidder, Tierra Contracting (a local vendor), subject to the provisions of documents and certifications, as set forth in the plans and specification applicable to the project and as required by law;
 
b) Authorize the Chair to execute the construction contract upon return of the contractor's executed contract documents, and the review and approval of the County Counsel, Auditor-Controller, and Risk Manager or their authorized representatives;
 
c) Approve a contingency in the amount of $25,354.75 for the above subject project; and
 
d) Approve plans and specifications for the project.
 