File #: 11-00619    Version: 1
Type: Agenda Item Status: Passed
File created: In control: BOARD OF SUPERVISORS
On agenda: 8/9/2011 Final action: 8/9/2011
Title: Acting as the Board of Directors, Flood Control and Water Conservation District: Consider recommendations regarding the March 2011 Storm Repair Project for Bradley Channel, Fifth District, as follows: a) Award of the Construction Contract for the March 2011 Storm Repair Project for Bradley Channel in the amount of $122,959.00 to the lowest responsible bidder, Brough Construction, Inc., subject to the provisions of documents and certifications as set forth in the plans and specification applicable to the project and as required by law; b) Approve and authorize the Chair to execute the Construction Contract upon return of the contractor’s executed contract documents, and the review and approval of the County Counsel, Auditor-Controller, and Risk Manager or their authorized representatives; c) Approve a contingency in the amount of $12,295.90 for the above subject project; and d) Approve plans and specifications for the project.
Sponsors: PUBLIC WORKS DEPARTMENT, BOARD OF DIRECTORS, FLOOD CONTROL AND WATER CONSER
Attachments: 1. Board Letter, 2. Construction Contract

Title

 

Acting as the Board of Directors, Flood Control and Water Conservation District:

 

Consider recommendations regarding the March 2011 Storm Repair Project for Bradley Channel, Fifth District, as follows:

 

a) Award of the Construction Contract for the March 2011 Storm Repair Project for Bradley Channel in the amount of $122,959.00 to the lowest responsible bidder, Brough Construction, Inc., subject to the provisions of documents and certifications as set forth in the plans and specification applicable to the project and as required by law;

 

b) Approve and authorize the Chair to execute the Construction Contract upon return of the contractor’s executed contract documents, and the review and approval of the County Counsel, Auditor-Controller, and Risk Manager or their authorized representatives;

 

c) Approve a contingency in the amount of $12,295.90 for the above subject project; and

 

d) Approve plans and specifications for the project.