Title
Consider recommendations regarding the Santa Barbara County Courthouse Hall of Records Rehabilitation, Interior Work Site # F02001 (Project # 8644), First District, as follows:
a) Approve and execute Amendment No. 1 to the contract with Urquidez Construction (BC 04-189) for unanticipated changes in the elevator installation in the amount of $22,676 for Phase II contract work in an amount not to exceed $227,476.
b) Approve and execute Amendment No. 1 to the contract with Urquidez Construction (BC 05-141) for unanticipated and additional scope of work in the amount of $506,500 for Phase III contract work in an amount not to exceed $1,422,537;
c) Approve the Budget Revision in the amount $656,279 (BJE2005615) from the Clerk-Recorder-Assessor Modernization Designation ($424,279), Deferred Maintenance appropriation ($196,000), and Asbestos Project ($36,000).
Body
[Enter body here.]