Title
Consider recommendations regarding Amendment No. 2 to the agreement for inspection services for the Montecito Creek Debris Basin Project with MNS Engineers, Inc., First District, as follows:
a) Approve and authorize the Chair to execute Amendment No. 2 to the agreement with MNS Engineers, Inc. in the amount of $75,000 from $185,500 to a total not to exceed $261,500 and extending the contract end date from February 28, 2002 to June 30, 2002;
b) Increase the 15% contingency fund from $27,975 to $39,225 for additional work that may be needed to complete the project.
Body
[Enter body here.]