File #: 00-00102    Version: 1
Type: Agenda Item Status: Passed
File created: 12/11/2000 In control: BOARD OF SUPERVISORS
On agenda: 12/12/2000 Final action: 12/12/2000
Title: Approve and execute Amendment No. 1 to the Construction Agreement with Carroll Construction Company, Inc., a local vendor, for the Manning Park Youth Center Structural Upgrade in the amount of $47,813, for a total contract amount of $227,185. Extend the time period of the contract by two working days for a revised contract completion date of January 12, 2001, First District.
Sponsors: PARKS
Title
Approve and execute Amendment No. 1 to the Construction Agreement with Carroll Construction Company, Inc., a local vendor, for the Manning Park Youth Center Structural Upgrade in the amount of $47,813, for a total contract amount of $227,185.  Extend the time period of the contract by two working days for a revised contract completion date of January 12, 2001, First District.