File #: 07-01008    Version: 1
Type: Agenda Item Status: Passed
File created: 10/15/2007 In control: BOARD OF SUPERVISORS
On agenda: 10/23/2007 Final action: 10/23/2007
Title: Consider recommendations regarding the construction of Tieback Wall on East Camino Cielo at M.P. 1.3, County Project No. 05STRM (3T34), Third District, as follows: a) Approve plans and specifications for the Construction of Tieback Wall on East Camino Cielo at M.P. 1.3, County Project No. 05STRM (3T34); b) Award the construction contract in the amount of $359,356.00 to the lowest responsible bidder, Souza & Peterson Construction Company Inc. (not a local vendor), P.O. Box 2057, Nipomo, CA 93444, subject to the provisions of documents and certification, as set forth in the plans and specifications applicable to the project and as required by law; c) Authorize the chair to execute the construction contract upon return of the Contractor's executed contract documents and the review and approval of the County Counsel, Auditor-Controller, and Risk Manager or their authorized representatives; and d) Approve a contingency fund in the amount of $30,467.80 for the Construction of Tie...
Sponsors: PUBLIC WORKS DEPARTMENT
Attachments: 1. Board Letter
Title
Consider recommendations regarding the construction of Tieback Wall on East Camino Cielo at M.P. 1.3, County Project No. 05STRM (3T34), Third District, as follows:
 
a) Approve plans and specifications for the Construction of Tieback Wall on East Camino Cielo at M.P. 1.3, County Project No. 05STRM (3T34);
 
b) Award the construction contract in the amount of $359,356.00 to the lowest responsible bidder, Souza & Peterson Construction Company Inc. (not a local vendor), P.O. Box 2057, Nipomo, CA 93444, subject to the provisions of documents and certification, as set forth in the plans and specifications applicable to the project and as required by law;
 
c) Authorize the chair to execute the construction contract upon return of the Contractor's executed contract documents and the review and approval of the County Counsel, Auditor-Controller, and Risk Manager or their authorized representatives; and
 
d) Approve a contingency fund in the amount of $30,467.80 for the Construction of Tieback Wall on East Camino Cielo at M.P. 1.3, County Project No. 05STRM (3T34).
Body
[Enter body here.]