Title
Acting as the Board of Directors, Flood Control and Water Conservation District:
Consider recommendations regarding Amendment No. 1 to the Agreement for the Las Vegas/San Pedro Creeks Capacity Improvement Project, Second District, as follows:
a) Approve and authorize the Chair to execute Amendment No. 1 to the Agreement with HDR Engineering, Inc. (not a local vendor) for engineering design services of the Las Vegas/San Pedro Creeks Capacity Improvement Project amending the end date from October 15, 2013 to December 31, 2014; and
b) Determine, pursuant to 14 CCR 15162, that a Mitigated Negative Declaration (MND) was adopted for the Las Vegas-San Pedro Creeks Capacity Improvement Project on October 4, 2011, that no substantial changes are proposed in the project, no substantial changes have occurred with respect to the circumstances under which the project is undertaken, and no new information of substantial importance has been received with respect to the project or the mitigation measures, and therefore no new EIR or Negative Declaration is required for the approval of the recommended actions.