Title
Acting as the Board of Directors, Flood Control and Water Conservation District:
Consider recommendations regarding Mud Lake Siphon Improvement Project, Phase II, Fourth District, as follows:
a) Authorize the Public Works Director to advertise and receive bids for the Mud Lake Siphon Improvement Project, Phase II; and
b) Find that the proposed project (Mud Lake Siphon Improvement Project, Phase II) consists of minor trenching and backfilling where the surface is restored in order to replace the siphon pipe at an existing facility and that the proposed action is therefore exempt from the California Environmental Quality Act (CEQA) pursuant to CEQA Guideline Sections 14 CCR 15304 (f) minor alterations to land, and 14 CCR 15301 (d) existing facilities, and direct the Clerk of the Board to file a CEQA Notice of Exemption (NOE) for the proposed project.