File #: 01-01247    Version: 1
Type: Agenda Item Status: Passed
File created: 9/12/2001 In control: BOARD OF SUPERVISORS
On agenda: 9/18/2001 Final action: 9/18/2001
Title: Consider recommendations regarding the 2001 Goleta Slough Dredging Project, Second and Third Districts, as follows: a) Award a construction contract to the lowest responsible bidder, Cushman Contracting Corporation (a local vendor) in the amount of $393,450 subject to the provision of documents and certifications, as set forth in the plans and specifications applicable to the project and as required by law; b) Authorize the Chair to execute the construction contract upon return of the contractor's executed contract documents and the review and approval of County Counsel, Auditor-Controller and Risk Manager or their authorized representatives; c) Approve a contingency fund in the amount of $32,172.50 for the project.
Sponsors: BOARD OF DIRECTORS, FLOOD CONTROL AND WATER CONSER
Title
Consider recommendations regarding the 2001 Goleta Slough Dredging Project, Second and Third Districts, as follows:
 
a) Award a construction contract to the lowest responsible bidder, Cushman Contracting Corporation (a local vendor) in the amount of $393,450 subject to the provision of documents and certifications, as set forth in the plans and specifications applicable to the project and as required by law;
 
b) Authorize the Chair to execute the construction contract upon return of the contractor's executed contract documents and the review and approval of County Counsel, Auditor-Controller and Risk Manager or their authorized representatives;
 
c) Approve a contingency fund in the amount of $32,172.50 for the project.
 
Body
[Enter body here.]