File #: 02-00315    Version: 1
Type: Agenda Item Status: Passed
File created: 3/15/2002 In control: BOARD OF SUPERVISORS
On agenda: 3/26/2002 Final action: 3/26/2002
Title: Consider recommendations regarding 2001-02 Central and North County Measure D Concrete Repair, Tree Removal, Tree Root Pruning and Shielding (Project No. 820482), Third, Fourth and Fifth Districts, as follows: a) Approve plans and specifications for the project; b) Declare bid proposal submitted by Whitaker Contractors, Inc. (not a local vendor) for the project as non-responsive; c) Award the construction contract in the amount of $994,473.55 to the lowest responsible bidder, Mendez Concrete, Inc. (not a local vendor) subject to the provision of documents and certifications, as set forth in the plans and specifications applicable to the project and as required by law; d) Authorize the Chair to execute the construction contract upon return of the Contractor's executed contract documents, and the review and approval of the County Counsel, Auditor-Controller and Risk Manager or their authorized representatives; e) Approve a contingency fund in the amount of $62,223.68 ...
Sponsors: PUBLIC WORKS DEPARTMENT
Attachments: 1. Board Letter
Title
Consider recommendations regarding 2001-02 Central and North County Measure D Concrete Repair, Tree Removal, Tree Root Pruning and Shielding (Project No. 820482), Third, Fourth and Fifth Districts, as follows:
 
a)  Approve plans and specifications for the project;
 
b)  Declare bid proposal submitted by Whitaker Contractors, Inc. (not a local vendor) for the project as non-responsive;
 
c)  Award the construction contract in the amount of $994,473.55 to the lowest responsible bidder, Mendez Concrete, Inc. (not a local vendor) subject to the provision of documents and certifications, as set forth in the plans and specifications applicable to the project and as required by law;
 
d)  Authorize the Chair to execute the construction contract upon return of the Contractor's executed contract documents, and the review and approval of the County Counsel, Auditor-Controller and Risk Manager or their authorized representatives;
 
e)  Approve a contingency fund in the amount of $62,223.68 for the project.
Body
[Enter body here.]