Consider recommendations regarding Blosser Channel Improvements Project, Fifth District, as follows:
a) Award the construction contract in the amount of $824,130 to the lowest responsible bidder, JP Donovan Construction, Inc. (not a local vendor) subject to the provision of documents and certifications, as set forth in the plans and specifications applicable to the project and as required by law;
b) Authorize the Chair to execute the construction contract upon return of the Contractor's executed contract documents, and the review and approval of the County Counsel, Auditor-Controller and Risk Manager or their authorized representatives;
c) Approve a contingency fund in the amount of $53,706.50 for the project.