File #: 13-00877    Version: 1
Type: Agenda Item Status: Passed
File created: In control: BOARD OF SUPERVISORS
On agenda: 12/3/2013 Final action: 12/3/2013
Title: Consider recommendations regarding Lillingston Canyon Debris Basin Phase 3 Removal Project Statement of Final Quantities, First District, as follows: a) Approve and authorize the Chair to execute the Statement of Final Quantities for work performed and materials supplied for the Lillingston Canyon Debris Basin Phase 3 Removal Project by the contractor Acacia Erosion Control, Inc. in the amount of $198,739.70; and b) Find that pursuant to the California Environmental Quality Act (CEQA) Guidelines Section 15162, no new effects will occur and no new mitigation measures would be required as a result of the project, and therefore, pursuant to CEQA Section 15168 (c)(2),the Lillingston Canyon Debris Basin Project is within the scope of the project covered by the Program Environmental Impact Report (PEIR) for the Updated Routine Maintenance Program (01-EIR-01), Findings, and Statement of Overriding Considerations approved in December, 2001, and the Lillingston Debris Basin addendum to th...
Sponsors: PUBLIC WORKS DEPARTMENT, BOARD OF DIRECTORS, FLOOD CONTROL AND WATER CONSER
Attachments: 1. Board Letter, 2. Statement of Final Quantities
Title
 
Consider recommendations regarding Lillingston Canyon Debris Basin Phase 3 Removal Project Statement of Final Quantities, First District, as follows:
 
a) Approve and authorize the Chair to execute the Statement of Final Quantities for work performed and materials supplied for the Lillingston Canyon Debris Basin Phase 3 Removal Project by the contractor Acacia Erosion Control, Inc. in the amount of $198,739.70; and
 
b) Find that pursuant to the California Environmental Quality Act (CEQA) Guidelines Section 15162, no new effects will occur and no new mitigation measures would be required as a result of the project, and therefore, pursuant to CEQA Section 15168 (c)(2),the Lillingston Canyon Debris Basin Project is within the scope of the project covered by the Program Environmental Impact Report (PEIR) for the Updated Routine Maintenance Program (01-EIR-01), Findings, and Statement of Overriding Considerations approved in December, 2001, and the Lillingston Debris Basin addendum to the PEIR approved June 15, 2010, and no new environmental document is required.