Title
Consider recommendations regarding the construction of the total Dissolved Solids and Recycled Water Project (BRINEX #860031), Fourth and Fifth Districts, as follows:
a) Approve plans and specifications for construction of the project;
b) Award and authorize the Chair to execute the construction contract in the amount of $7,998,000 to the lowest responsible bidder, Cushman Contracting Corporation (a local vendor), subject to the provisions of documents and certification, as set forth in the plans and specifications applicable to the project, as required under California law;
c) Approve a contingency fund in the amount of $150,000 for construction of the Total Dissolved Solids and Recycled Water Project.
Body
[Enter body here.]