File #: 04-00356    Version: 1
Type: Agenda Item Status: Passed
File created: 4/5/2004 In control: BOARD OF SUPERVISORS
On agenda: 4/13/2004 Final action: 4/13/2004
Title: Review and approve the Statement of Final Quantities for work performed and materials supplied by AIS Construction Company (a local vendor) for storm damage repair of Stagecoach Road (Project No. 03STRM-3T01), in the amount of $303,506.25, Third District.
Sponsors: PUBLIC WORKS DEPARTMENT
Attachments: 1. Board Letter
Title
Review and approve the Statement of Final Quantities for work performed and materials supplied by AIS Construction Company (a local vendor) for storm damage repair of Stagecoach Road (Project No. 03STRM-3T01), in the amount of  $303,506.25, Third District.
 
Body
[Enter body here.]