Legislation Details

File #: 26-00847    Version: 1
Type: Administrative Item Status: Agenda Ready
File created: 9/4/2026 In control: BOARD OF SUPERVISORS
On agenda: 9/15/2026 Final action:
Title: Consider recommendations regarding Laguna County Sanitation District Treatment Plant Legacy Facilities Decommissioning Project Award, Fourth and Fifth Districts, as follows: Acting as the Board of Directors, Laguna County Sanitation District: a) Approve the plans and specifications for the Laguna County Sanitation District Treatment Plant Legacy Facilities Decommissioning Project, on file in the Laguna County Sanitation District office; b) Award the Construction Contract in the base amount of $1,365,500.00 to W.M. Lyles Co., the lowest responsible bidder, subject to the provision of documents and certifications required under California law and the project specifications; c) Authorize the Public Works Director or designee to approve change orders for a contingency amount up to $75,000.00, for a total not-to-exceed contract authorization of $1,441,500.00; d) Approve and authorize the Chair to execute the Construction Contract with W.M. Lyles Co.; and e) Determine that the action i...
Sponsors: PUBLIC WORKS DEPARTMENT, BOARD OF DIRECTORS, LAGUNA COUNTY SANITATION DISTR
Attachments: 1. Board Letter, 2. Attachment A - Construction_Contract, 3. Attachment B - Notice of Exemption (1)
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

 

Consider recommendations regarding Laguna County Sanitation District Treatment Plant Legacy Facilities Decommissioning Project Award, Fourth and Fifth Districts, as follows:

 

Acting as the Board of Directors, Laguna County Sanitation District:

 

a) Approve the plans and specifications for the Laguna County Sanitation District Treatment Plant Legacy Facilities Decommissioning Project, on file in the Laguna County Sanitation District office;

 

b) Award the Construction Contract in the base amount of $1,365,500.00 to W.M. Lyles Co., the lowest responsible bidder, subject to the provision of documents and certifications required under California law and the project specifications;

 

c) Authorize the Public Works Director or designee to approve change orders for a contingency amount up to $75,000.00, for a total not-to-exceed contract authorization of $1,441,500.00;

 

d) Approve and authorize the Chair to execute the Construction Contract with W.M. Lyles Co.; and

 

e) Determine that the action is categorically exempt under the California Environmental Quality Act (CEQA) pursuant to Section 15301(b) (Existing Facilities) and Section 15302(c) (Replacement or Reconstruction) of Chapter 3 of Title 14 of the California Code of Regulations (State CEQA Guidelines) and approve the posting of a Notice of Exemption on that basis.