Title: Consider recommendations regarding the Serenidad Interceptor Channel Project (SC8318) to increase capacity for flood generated debris, Second District, as follows: a) Award the construction contract in the amount of $221,640 to the lowest responsible bidder Spiess Construction Company Inc., (a local vendor) subject to the provisions of documents and certifications, as set forth in the plans and specification applicable to the project and as required by law; b) Authorize the Chair to execute the construction contract upon return of the contractor's executed contract documents, and the review and approval of the County Counsel, Auditor-Controller, and Risk Manager or their authorized representatives; c) Approve a 10% contingency fund in the amount of $22,164.00 for the project.
Sponsors: BOARD OF DIRECTORS, FLOOD CONTROL AND WATER CONSER
Attachments: 1. Board Letter
Title
Consider recommendations regarding the Serenidad Interceptor Channel Project (SC8318) to increase capacity for flood generated debris, Second District, as follows:
 
a)  Award the construction contract in the amount of $221,640 to the lowest responsible bidder Spiess Construction Company Inc., (a local vendor) subject to the provisions of documents and certifications, as set forth in the plans and specification applicable to the project and as required by law;
 
b)  Authorize the Chair to execute the construction contract upon return of the contractor's executed contract documents, and the review and approval of the County Counsel, Auditor-Controller, and Risk Manager or their authorized representatives;
 
c)  Approve a 10% contingency fund in the amount of $22,164.00 for the project.
 