Title
Consider recommendations regarding the Gobernador Debris Basin Modification Project, First District, as follows:
a) Approve and authorize the Chair to execute Contract Change Order No. 1 in the amount of $169,469.50 with Shaw Excavating and Grading for the Gobernador Debris Basin Modification Project; and
b) Retain the previously authorized contingency amount of $54,022.88 for future minor changes to the project