File #: 01-00301    Version: 1
Type: Agenda Item Status: Passed
File created: 4/4/2001 In control: BOARD OF SUPERVISORS
On agenda: 3/6/2001 Final action: 3/6/2001
Title: HEARING - Consider recommendations regarding the Five-Year Capital Improvement Program (CIP) and Fiscal Year 2001-02 Capital Budget, as follows: (EST. TIME: 1 HR. 30 MIN.) a) Approve in concept the projects included in the Fiscal Year 2001-02 CIP; b) Approve in concept the $76,781,000 included in the CIP for the FY 2001-02 Capital Budget; c) Refer the CIP to the Planning Commission and request analysis of major public works projects recommended for planning, initiation or construction during FY 2001-02 for conformity with the County Comprehensive Plan; d) Take final action to adopt the FY 2001-02 Capital Budget in June after considering the Proposed 2001-02 Operating Budget. Scheduled Presentations: Introduction - County Administrator's Office (EST. TIME: 5 MIN.) Public Works Projects (EST. TIME: 30 MIN.) Parks Projects (EST. TIME: 5 MIN.) County Building and Deferred Building Maintenance Projects (EST. TIME: 25 MIN.) COUNTY ADMINISTRATOR'S RECOMMENDA...
Sponsors: COUNTY EXECUTIVE OFFICE
Attachments: 1. D-3.pdf
Title
HEARING - Consider recommendations regarding the Five-Year Capital Improvement Program (CIP) and Fiscal Year 2001-02 Capital Budget, as follows:  (EST. TIME: 1 HR. 30 MIN.)  
 
a) Approve in concept the projects included in the Fiscal Year 2001-02 CIP;
 
b) Approve in concept the $76,781,000 included in the CIP for the FY 2001-02 Capital Budget;
 
c) Refer the CIP to the Planning Commission and request analysis of major public works projects recommended for planning, initiation or construction during FY 2001-02 for conformity with the County Comprehensive Plan;
 
d) Take final action to adopt the FY 2001-02 Capital Budget in June after considering the Proposed 2001-02 Operating Budget.
 
Scheduled Presentations:
 
Introduction - County Administrator's Office (EST. TIME: 5 MIN.)
 
Public Works Projects (EST. TIME: 30 MIN.)
 
Parks Projects (EST. TIME: 5 MIN.)
 
County Building and Deferred Building Maintenance Projects
(EST. TIME: 25 MIN.)
 
COUNTY ADMINISTRATOR'S RECOMMENDATION: APPROVE
 
 
 
 
Body
[Enter body here.]