Title
Consider recommendations regarding construction of 2005-06 County-Wide Measure 'D' Preventive Maintenance Application of Scrub Seal and Micro Surfacing (County Project No. 820603) as follows:
a) Approve plans and specifications for the project;
b) Award the construction contract to the lowest responsible bidder, Intermountain Slurry Seal, Inc. (Not a Local Vendor), subject to the provisions of documents and certification, as set forth in the plans and specifications applicable to the project and as required by law, in the amount of $989,989;
c) Authorize the Chair to execute the construction contract upon return of the Contractor's executed contract documents, and the review and approval of the County Counsel, Auditor-Controller and Risk Manager or their authorized representatives:
d) Approve a contingency fund in the amount of $61,999.45 for the project.
Body
[Enter body here.]