File #: 09-00121    Version:
Type: Agenda Item Status: Passed
File created: 1/29/2009 In control: BOARD OF SUPERVISORS
On agenda: 2/24/2009 Final action: 2/24/2009
Title: HEARING - Consider recommendations regarding Sheriff Tech Services/EOC Feasibility Study, as follows: (EST. TIME: 15 MIN.) a) Reject the proposal of siting the Emergency Operations Center (EOC) in the basement of the Main Jail/Sheriff's Headquarters Expansion project; b) Transfer $326,298 from the EOC project budget to the Main Jail/Sheriff's Headquarters Expansion project as these funds were originally transferred to the EOC project from the Sheriff Department; and c) Authorize the Sheriff to develop and bring forward the standalone Main Jail/Sheriff's Headquarters Expansion project at a cost of not to exceed $4,942,710 (except for additional interest accumulation on the COP funds). COUNTY EXECUTIVE OFFICER'S RECOMMENDATION: APPROVE
Sponsors: GENERAL SERVICES DEPARTMENT, SHERIFF-CORONER OFFICE
Attachments: 1. Board Letter 2/10/09, 2. Board Letter 2/24/09
Title
 
HEARING - Consider recommendations regarding Sheriff Tech Services/EOC Feasibility Study, as follows: (EST. TIME: 15 MIN.)
 
a) Reject the proposal of siting the Emergency Operations Center (EOC) in the basement of the Main Jail/Sheriff's Headquarters Expansion project;
 
b) Transfer $326,298 from the EOC project budget to the Main Jail/Sheriff's Headquarters Expansion project as these funds were originally transferred to the EOC project from the Sheriff Department; and
 
c) Authorize the Sheriff to develop and bring forward the standalone Main Jail/Sheriff's Headquarters Expansion project at a cost of not to exceed $4,942,710 (except for additional interest accumulation on the COP funds).
 
COUNTY EXECUTIVE OFFICER'S RECOMMENDATION: APPROVE
 
Body
[Enter body here.]