Title
Consider recommendations regarding the 2000-01 General Fund Miscellaneous Concrete Repair, Tree Root Pruning, Shielding and Asphalt Concrete Overlay at various locations in the Goleta Valley area, Second and Third Districts, as follows:
a) Approve plans and specifications for the project;
b) Award the construction contract to the lowest responsible bidder, Granite Construction Company (not a local vendor) in the amount of $772,367, subject to the provision of documents and certifications, as set forth in the plans and specifications applicable to the project and as required by law;
c) Authorize the Chair to execute the construction contract upon return of the Contractor's executed contract documents and the review and approval of County Counsel, Auditor-Controller and Risk Manager or their representatives;
d) Approve a contingency fund in the amount of $51,118.35 for the project.
Body
[Enter body here.]