File #: 05-01022    Version: 1
Type: Agenda Item Status: Passed
File created: 10/28/2005 In control: BOARD OF SUPERVISORS
On agenda: 11/8/2005 Final action: 11/8/2005
Title: Approve and authorize the Chair to execute Amendment No. 3, in the amount of $150,858, to the construction contract 04-182 with S.J. Deferville Construction, Inc. (a local vendor) for construction change orders associated with the Public Works Service Center project, for a revised Contract total of $2,464,706, Fifth District.
Sponsors: GENERAL SERVICES DEPARTMENT
Attachments: 1. Board Letter
Title
Approve and authorize the Chair to execute Amendment No. 3, in the amount of $150,858, to the construction contract 04-182 with S.J. Deferville Construction, Inc. (a local vendor) for construction change orders associated with the Public Works Service Center project, for a revised Contract total of $2,464,706, Fifth District.
 
Body
[Enter body here.]