File #: 02-01237    Version: 1
Type: Agenda Item Status: Passed
File created: 12/2/2002 In control: BOARD OF SUPERVISORS
On agenda: 12/10/2002 Final action: 12/10/2002
Title: Consider recommendations regarding construction of Goleta Beach Pier Pile Replacement and Structural Repairs (Project No. D42516), Second District, as follows: a) Declare bid proposal submitted by Associated Pacific Constructors, Inc.(not a local vendor) for the Construction of Goleta Pier Pile Replacement and Structural Repairs, as non-responsive; b) Award and execute the construction contract in the amount of $51,850 to the lowest responsible bidder, Schock-Hanly Corporation, (a local vendor) subject to the provision of documents and certifications, as set forth in the plans and specifications applicable to the project and as required by law.
Sponsors: PARKS
Attachments: 1. Board Letter
Title
Consider recommendations regarding construction of Goleta Beach Pier Pile Replacement and Structural Repairs (Project No. D42516), Second District, as follows:
 
a)  Declare bid proposal submitted by Associated Pacific Constructors, Inc.(not a local vendor) for the Construction of Goleta Pier Pile Replacement and Structural Repairs, as non-responsive;
 
b)  Award and execute the construction contract in the amount of $51,850 to the lowest responsible bidder, Schock-Hanly Corporation, (a local vendor) subject to the provision of documents and certifications, as set forth in the plans and specifications applicable to the project and as required by law.
 
Body
[Enter body here.]