Title: Consider recommendations regarding the Isla Vista Continuous Deflective Separation Project, Third District, as follows: a) Award the construction contract in the amount of $179,650 to the lowest responsible bidder Lash Construction (a local vendor) subject to the provisions of documents and certifications, as set forth in the plans and specification applicable to the project and as required by law; b) Authorize the Chair to execute the construction contract upon return of the contractor's executed contract documents, and the review and approval of the County Counsel, Auditor-Controller, and Risk Manager or their authorized representatives; c) Approve plans and specifications for the project; d) Approve a 10% contingency fund in the amount of $17,965 for the above subject project.
Sponsors: PUBLIC WORKS DEPARTMENT
Attachments: 1. Board Letter
Title
Consider recommendations regarding the Isla Vista Continuous Deflective Separation Project, Third District, as follows:
 
a)  Award the construction contract in the amount of $179,650 to the lowest responsible bidder Lash Construction (a local vendor) subject to the provisions of documents and certifications, as set forth in the plans and specification applicable to the project and as required by law;
 
b)  Authorize the Chair to execute the construction contract upon return of the contractor's executed contract documents, and the review and approval of the County Counsel, Auditor-Controller, and Risk Manager or their authorized representatives;
 
c)  Approve plans and specifications for the project;
 
d)        Approve a 10% contingency fund in the amount of $17,965 for the above subject project.
 