Title: Consider recommendations regarding the Construction of Montecito Pedestrian Bridge at Oak Creek, Safe Route to School, at Santa Rosa Lane in the Montecito Area, County Project No. 862254, First District, as follows: a) Approve plans and specifications for the Construction of Montecito Pedestrian Bridge at Oak Creek, Safe Route to School, at Santa Rosa Lane in the Montecito Area; b) Award the construction contract in the amount of $293,186.00 to the lowest responsible bidder, JMA Construction Company, 9909 Topanga Blvd #224, Chatsworth, CA 91311, a California corporation (not a local vendor), subject to the provision of documents and certifications, and set forth in the plans and specifications applicable to the project and as required by law; c) Authorize the Chair to execute the construction contract upon return of the Contractor's executed contract documents and the review and approval of the County Counsel, Auditor-Controller, and Risk Manager or their authorized represent...
Sponsors: PUBLIC WORKS DEPARTMENT
Attachments: 1. Board Letter, 2. Contract
Title
Consider recommendations regarding the Construction of Montecito Pedestrian Bridge at Oak Creek, Safe Route to School, at Santa Rosa Lane in the Montecito Area, County Project No. 862254, First District, as follows:
 
a) Approve plans and specifications for the Construction of Montecito Pedestrian Bridge at Oak Creek, Safe Route to School, at Santa Rosa Lane in the Montecito Area;
 
b) Award the construction contract in the amount of $293,186.00 to the lowest responsible bidder, JMA Construction Company, 9909 Topanga Blvd #224, Chatsworth, CA 91311, a California corporation (not a local vendor), subject to the provision of documents and certifications, and set forth in the plans and specifications applicable to the project and as required by law;
 
c) Authorize the Chair to execute  the construction contract upon return of the Contractor's executed contract documents and the review and approval of the County Counsel, Auditor-Controller, and Risk Manager or their authorized representatives; and
 
d) Approve a contingency in the amount of $27,159.30 for Construction of Montecito Pedestrian Bridge at Oak Creek, Safe Route to School, at Santa Rosa Lane in the Montecito Area.