Title: Consider recommendations regarding the Foxen Canyon Landfill Final Closure Project No. 170011, Third District, as follows: For the award of the construction contract: a) Approve plans and specifications for Foxen Canyon Landfill (FCL) Final Closure, Project No. 170011; b) Award the construction contract in the amount of $2,567,185.50 to the lowest responsible bidder, Whitaker Contractors, Inc., (not a loal vendor) subject to the provisions of documents and certification, as set forth in the plans and specifications applicable to the project, as required under California Law; c) Authorize the Chair to execute the construction contract upon return of the Contractors executed contract documents and the review and approval of the County Counsel, Auditor-Controller and Risk Manager or their authorized representatives; d) Approve Contingency Fund in the amount of $140,859.28 for FCL Final Closure, Project No. 170011; and For the acquisition of professional consulting ser...
Sponsors: PUBLIC WORKS DEPARTMENT
Attachments: 1. Board Letter, 2. Attachment A, 3. Attachment B, 4. Attachment C
Title
Consider recommendations regarding the Foxen Canyon Landfill Final Closure Project No. 170011, Third District, as follows:
      
For the award of the construction contract:
      
a) Approve plans and specifications for Foxen Canyon Landfill (FCL) Final Closure, Project No. 170011;
 
b) Award the construction contract in the amount of $2,567,185.50 to the lowest responsible bidder, Whitaker Contractors, Inc., (not a loal vendor) subject to the provisions of documents and certification, as set forth in the plans and specifications applicable to the project, as required under California Law;
 
c) Authorize the Chair to execute the construction contract upon return of the Contractors executed contract documents and the review and approval of the County Counsel, Auditor-Controller and Risk Manager or their authorized representatives;
 
d) Approve Contingency Fund in the amount of $140,859.28 for FCL Final Closure, Project No. 170011; and
 
For the acquisition of professional consulting services:
 
e) Approve the appointment of SCS Engineers (not a loal vendor) to provide Project Management Services for the FCL Final Closure construction contract for an amount of $98,380.00 and authorize the Chair to execute after review and approval of County Counsel, Auditor-Controller and Risk Manager or their authorized representatives; and
 
f) Approve the appointment of GeoSyntec Consultants (not a loal vendor) to provide Construction Quality Assurance (CQA) Services for the FCL Final Closure construction contract for an amount of $137,004.00 and authorize the Chair to execute after review and approval of County Counsel, Auditor-Controller and Risk Manager or their authorized representatives.
Body
[Enter body here.]