Title: Consider recommendations regarding the Construction of Zaca Fire Repair on Santa Barbara Canyon Road, Santa Barbara County Project No. 810533, Fifth District, as follows: a) Accept a Notice of Completion for work performed by the Contractor, Union Asphalt, Inc. (a local vendor), 1625 East Donovan Road, Santa Maria, California 93454; and b) Review and approve the Statement of Final Quantities for work performed and materials supplied for this project by the Contractor, in the amount of $322,649.36.
Sponsors: PUBLIC WORKS DEPARTMENT
Attachments: 1. Board Letter, 2. Notice of Completion, 3. Statement of Final Quantities
Title
 
Consider recommendations regarding the Construction of Zaca Fire Repair on Santa Barbara Canyon Road, Santa Barbara County Project No. 810533, Fifth District, as follows:
 
a) Accept a Notice of Completion for work performed by the Contractor, Union Asphalt, Inc. (a local vendor), 1625 East Donovan Road, Santa Maria, California 93454; and
 
b) Review and approve the Statement of Final Quantities for work performed and materials supplied for this project by the Contractor, in the amount of $322,649.36.
 
 