File #: 02-00348    Version: 1
Type: Agenda Item Status: Passed
File created: 3/22/2002 In control: BOARD OF SUPERVISORS
On agenda: 4/2/2002 Final action: 4/2/2002
Title: Consider recommendations regarding an Agreement for Construction Inspection Services for the Blosser Channel Improvement Project with Fugro West, Inc. (not a local vendor), Fifth District, as follows: a) Authorize the Chair to execute an Agreement with Fugro West Inc., for construction inspection services for the Blosser Channel Improvement Project for the period of March 19, 2002 through June 30, 2003, in an amount not to exceed $78,000; b) Authorize a 15% contingency fund in the amount of $11,700 for additional work that may be needed to complete the project.
Sponsors: BOARD OF DIRECTORS, FLOOD CONTROL AND WATER CONSER
Attachments: 1. Board Letter
Title
Consider recommendations regarding an Agreement for Construction Inspection Services for the Blosser Channel Improvement Project with Fugro West, Inc. (not a local vendor), Fifth District, as follows:
 
a)  Authorize the Chair to execute an Agreement with Fugro West Inc., for construction inspection services for the Blosser Channel Improvement Project for the period of March 19, 2002 through June 30, 2003, in an amount not to exceed $78,000;
 
b)        Authorize a 15% contingency fund in the amount of $11,700 for additional work that may be needed to complete the project.
 
Body
[Enter body here.]