Title
Set a hearing to Consider recommendations regarding the Ceres Farm, LLC Appeal of the Planning Commission Approval of the Ceres Farm Mixed-Light Cannabis Cultivation Project, Case Nos. 22APL-000000-00028 and 19CDP-00000-00015, First District, as follows:
(Set a hearing for December 13, 2022. Time estimate: 1 hour)
a) Grant the appeal, Case No. 22APL-00000-00028;
b) Make the required findings for approval of the Project, Case No. 19CDP-00000-00015, including California Environmental Quality Act (CEQA) findings;
c) Determine that the previously certified Programmatic Environmental Impact Report (PEIR) (17EIR-00000-00003) is adequate and no subsequent Environmental Impact Report or Negative Declaration is required pursuant to CEQA Guidelines Sections 15162 and 15168(c)(2); and
d) Grant de novo approval of the Project, Case No. 19CDP-00000-00015, subject to the conditions of approval; or
Alternatively, in order to deny the appeal and approve the project, take the following actions:
a) Deny the appeal, Case No. 22APL-00000-00028;
b) Make the required findings for approval of the Project, Case No. 19CDP-00000-00015, including CEQA findings;
c) Determine that the previously certified PEIR (17EIR-00000-00003) is adequate and no subsequent Environmental Impact Report or Negative Declaration is required pursuant to CEQA Guidelines Sections 15162 and 15168(c)(2); and
d) Grant de novo approval of the Project, Case No. 19CDP-00000-00015, subject to the conditions of approval, including Condition No. 37 (Odor Abatement Plan Revision), as conditioned by the Planning Commission.