File #: 09-00463    Version: 1
Type: Agenda Item Status: Passed
File created: 5/7/2009 In control: BOARD OF SUPERVISORS
On agenda: 5/19/2009 Final action: 5/19/2009
Title: Consider recommendations regarding the construction of Cachuma Lake Sewer Lift Station No. 3 Improvements, Project No. D00099, Third District, as follows: a) Approve the plans and specifications for the construction of Cachuma Lake Sewer Lift Station No. 3 Improvements, Project No. D00099; b) Award the construction contract in the amount of $676,911.00 to the lowest responsible bidder, Raminha Construction Inc., located at 6805 Sycamore Road, Atascadero, CA 93422 (not a local vendor), subject to the provisions of documents and certifications as set forth in the plans and specifications applicable to the project as required under California law; c) Approve and authorize the Chair to execute the construction contract upon return of the contractor's executed contract documents, and upon the review and approval of the County Counsel, Auditor-Controller, and Risk Manager or their authorized representatives; and d) Approve a contingency fund in the amount of $46,345.55 for the co...
Sponsors: PARKS
Attachments: 1. Board Letter, 2. Contract
Title
 
Consider recommendations regarding the construction of Cachuma Lake Sewer Lift Station No. 3 Improvements, Project No. D00099, Third District, as follows:
 
a) Approve the plans and specifications for the construction of Cachuma Lake Sewer Lift Station No. 3 Improvements, Project No. D00099;
 
b) Award the construction contract in the amount of $676,911.00 to the lowest responsible bidder, Raminha Construction Inc., located at 6805 Sycamore Road, Atascadero, CA 93422 (not a local vendor), subject to the provisions of documents and certifications as set forth in the plans and specifications applicable to the project as required under California law;
 
c) Approve and authorize the Chair to execute the construction contract upon return of the contractor's executed contract documents, and upon the review and approval of the County Counsel, Auditor-Controller, and Risk Manager or their authorized representatives; and
 
d) Approve a contingency fund in the amount of $46,345.55 for the construction of Cachuma Lake Sewer Lift Station No. 3 Improvements.
 