File #: 11-00385    Version: 1
Type: Agenda Item Status: Passed
File created: 4/29/2011 In control: BOARD OF SUPERVISORS
On agenda: 5/10/2011 Final action: 5/10/2011
Title: Consider recommendations regarding the Reconstruction of a Portion of Harris Grade Road HR3 Project, Federal Project No. HRRRL-5951(115), County Project No. 862273, Fourth District, as follows: a) Accept the Notice of Completion for the reconstruction of a portion of Harris Grade Road for work performed by the Contractor, Rockwood General Contractors, Inc. (not a local vendor), Post Office Box 1529, Nipomo, California 93444; and b) Approve and authorize the Chair to execute the Statement of Final Quantities for the Reconstruction of a Portion of Harris Grade Road HR3 Project for work performed and materials supplied by Rockwood General Contractors in the amount of $295,605.51.
Sponsors: PUBLIC WORKS DEPARTMENT
Attachments: 1. Board Letter, 2. Notice of Completion, 3. Statement of Final Quantities

Title

Consider recommendations regarding the Reconstruction of a Portion of Harris Grade Road HR3 Project, Federal Project No.  HRRRL-5951(115), County Project No. 862273, Fourth District, as follows:

 

a) Accept the Notice of Completion for the reconstruction of a portion of Harris Grade Road for work performed by the Contractor, Rockwood General Contractors, Inc. (not a local vendor), Post Office Box 1529, Nipomo, California 93444; and

 

b) Approve and authorize the Chair to execute the Statement of Final Quantities for the Reconstruction of a Portion of Harris Grade Road HR3 Project for work performed and materials supplied by Rockwood General Contractors in the amount of $295,605.51.