Title: Consider recommendations regarding the Laguna County Sanitation District Recycled Water Tank and System Improvement project (WTHOLD), Fourth District, as follows: a) Approve plans and specifications for the Recycled Water Tank and System Improvement project; b) Award the construction contract in the amount of $1,235,641.00 to the lowest responsible bidder, V. Lopez, Jr. and Sons, Inc. (a local vendor), located at 200 East Fesler Street, Apt. 101, Santa Maria, CA 93454 subject to the provision of documents and certifications, as set forth in the plans and specifications applicable to the project, as required under California law; c) Approve and authorize the Chair to execute the construction contract, upon return of the contractor's executed documents, and review and approval of the County Counsel, Auditor-Controller and Risk Manager or their authorized representatives; and d) Approve a contingency fund in the amount of $74,282.05 for the project.
Sponsors: PUBLIC WORKS DEPARTMENT, BOARD OF DIRECTORS, LAGUNA COUNTY SANITATION DISTR
Attachments: 1. Recycled Water Tank and System Improvement Board Letter, 2. V. Lopez Jr. and Sons, Inc. Contract
Title
 
Consider recommendations regarding the Laguna County Sanitation District Recycled Water Tank and System Improvement project (WTHOLD), Fourth District, as follows:
 
a) Approve plans and specifications for the Recycled Water Tank and System Improvement project;
 
b) Award the construction contract in the amount of $1,235,641.00 to the lowest responsible bidder, V. Lopez, Jr. and Sons, Inc. (a local vendor), located at 200 East Fesler Street, Apt. 101, Santa Maria, CA 93454 subject to the provision of documents and certifications, as set forth in the plans and specifications applicable to the project, as required under California law;
 
c) Approve and authorize the Chair to execute the construction contract, upon return of the contractor's executed documents, and review and approval of the County Counsel, Auditor-Controller and Risk Manager or their authorized representatives; and
 
d) Approve a contingency fund in the amount of $74,282.05 for the project.
 