Title:
|
Consider recommendations regarding the construction of 2000-01 County-Wide Measure D Preventive Maintenance Application of Fog Seal, All Districts, as follows:
a) Approve plans and specifications for the project;
b) Award and authorize the Chair to execute the construction contract in the amount of $546,359.10 to the lowest responsible bidder, Western States Surfacing, Inc. (not a local vendor) subject to the provisions of documents and certification, as set forth in the plans and specifications applicable to the project, as required under California law;
c) Approve a contingency fund in the amount of $39,817.96 for the project.
|