File #: 09-00999    Version: 1
Type: Agenda Item Status: Passed
File created: 11/20/2009 In control: BOARD OF SUPERVISORS
On agenda: 12/1/2009 Final action: 12/1/2009
Title: Consider recommendations regarding the construction of storm damage repair on Greenwell Avenue at Mile Post 0.25 north of Via Real, County Project No. 862259, Federal Project No. ER-4200(007), First District, as follows: a) Approve the plans and specifications for the construction of storm damage repair on Greenwell Avenue, County Project No. 862259; b) Award the construction contract in the amount of $321,354.39 to the lowest responsible bidder, Berry General Engineering (not a local vendor), Post Office Box 1457, Ventura, California, 93002, subject to the provision of documents and certifications, as set forth in the plans and specifications applicable to the project, as required under California Law; c) Approve and authorize the Chair to execute the construction contract upon return of the contractor’s executed contract document, and the review and approval of County Counsel, Auditor-Controller and Risk Management or their authorized representatives; and d) Approve a contingenc...
Sponsors: PUBLIC WORKS DEPARTMENT
Attachments: 1. Board Letter, 2. Contract

Title

Consider recommendations regarding the construction of storm damage repair on Greenwell Avenue at Mile Post 0.25 north of Via Real, County Project No. 862259, Federal Project No. ER-4200(007), First District, as follows:

 

a) Approve the plans and specifications for the construction of storm damage repair on Greenwell Avenue, County Project No. 862259;

 

b) Award the construction contract in the amount of $321,354.39 to the lowest responsible bidder, Berry General Engineering (not a local vendor), Post Office Box 1457, Ventura, California, 93002, subject to the provision of documents and certifications, as set forth in the plans and specifications applicable to the project, as required under California Law;

 

c) Approve and authorize the Chair to execute the construction contract upon return of the contractor’s executed contract document, and the review and approval of County Counsel, Auditor-Controller and Risk Management or their authorized representatives; and

 

d)  Approve a contingency fund in the amount of $28,567.72 for the Construction of Storm Damage Repair on Greenwell Avenue, County Project No. 862259.