Title
Consider recommendations regarding the South Turnpike Urban Runoff Treatment Control Pilot Project, Second District, as follows:
a) Award the construction contract to the lowest responsible bidder, V. Lopez and Sons (a local vendor) in the amount of $229,136.80, subject to the provision of documents and certifications, as set forth in the plans and specifications applicable to the project and as required by law;
b) Authorize the Chair to execute the construction contract upon return of the contractor's executed contract documents, and the review and approval of County Counsel, Auditor-Controller and Risk Manager or their authorized representatives;
c) Approve a 10% contingency fund in the amount of $22,913.68 for the project.
Body
[Enter body here.]