Title: Consider recommendations regarding the construction of Cable Mesh Drapery System on Stagecoach Road, County Project No. 862266, Federal Project No. ER-4200 (008), Third District, as follows: (4/5 Vote Required) a) Approve the plans and specifications for the construction of Stagecoach Road Storm Damage Repairs, Cable Mesh Drapery System, near the City of Santa Barbara; b) Award the construction contract in the amount of $289,398.35 to the lowest bidder, AIS Construction Company (a local vendor), 6240 Via Real, Suite 6, Carpinteria, CA 93013, subject to the provision of documents and certifications, as set forth in the plans and specifications applicable to the project, as required under California Law; c) Approve and authorize the Chair to execute the construction contract upon return of the Contractor's executed contract documents, and the review and approval of County Counsel, Auditor-Controller and Risk Management or their authorized representatives; d) Approve contingen...
Sponsors: PUBLIC WORKS DEPARTMENT
Attachments: 1. Board Letter, 2. Budget Revision Request
Title
Consider recommendations regarding the construction of Cable Mesh Drapery System on Stagecoach Road, County Project No. 862266, Federal Project No. ER-4200 (008), Third District, as follows: (4/5 Vote Required)
 
a) Approve the plans and specifications for the construction of Stagecoach Road Storm Damage Repairs, Cable Mesh Drapery System, near the City of Santa Barbara;
 
b) Award the construction contract in the amount of $289,398.35 to the lowest bidder, AIS Construction Company (a local vendor), 6240 Via Real, Suite 6, Carpinteria, CA 93013, subject to the provision of documents and certifications, as set forth in the plans and specifications applicable to the project, as required under California Law;
 
c) Approve and authorize the Chair to execute the construction contract upon return of the Contractor's executed contract documents, and the review and approval of County Counsel, Auditor-Controller and Risk Management or their authorized representatives;
 
d) Approve contingency funds in the amount of $26,969.92 for the Construction of Stagecoach Road Storm Damage Repairs, Cable Mesh Drapery System; and
 
e) Approve the Public Works Budget Revision Request for $361,000.00.