Title: Consider recommendations regarding El Colegio Road Improvements - Phase II, Professional Design Services Contract, County Project No. 864042, Third District, as follows: a) Approve and authorize the Chair to execute an agreement with Penfield and Smith Engineering (a local vendor), for professional design services for El Colegio Road Improvements, Phase II, Project Number 864042, at a total cost of $257,500; b) Authorize the Director of Public Works to approve amendments to the agreement for supplemental work up to $25,000; and c) Approve a budget revision No. 0000244 to accept the funds from the 1990 Long Range Development Plan Trust Fund and program for the El Colegio Road Phase II project.
Sponsors: PUBLIC WORKS DEPARTMENT
Attachments: 1. Board Letter, 2. Budget Revision Request, 3. Letter from US Department of Agriculture, 4. Letter of Continuance, 5. 6/3 Letter of Continuance
Title
Consider recommendations regarding El Colegio Road Improvements - Phase II, Professional Design Services Contract, County Project No. 864042, Third District, as follows:
 
a) Approve and authorize the Chair to execute an agreement with Penfield and Smith Engineering (a local vendor), for professional design services for El Colegio Road Improvements, Phase II, Project Number 864042, at a total cost of $257,500;
 
b) Authorize the Director of Public Works to approve amendments to the agreement for supplemental work up to $25,000; and
 
c) Approve a budget revision No. 0000244 to accept the funds from the 1990 Long Range Development Plan Trust Fund and program for the El Colegio Road Phase II project.
 
Body