Title:
|
Acting as the Board of Directors, Flood Control and Water Conservation District:
Consider recommendations regarding the Mission Creek Fish Passage Project, First and Second Districts, as follows:
a) Acting as a Responsible Agency under CEQA, approve the Mission Creek Fish Passage Project;
b) Find that the proposed modification of the Mission Creek channel is exempt under California Environmental Quality Act (CEQA) guidelines, Section 15333 Small Restoration Projects and Section 15301(B) Existing Facilities, pertaining to the modification of the concrete channel to allow for fish passage for steelhead and that this project will not result in adverse significant impacts on endangered, rare or threatened species or their habitat, that this modification is within an existing concrete lined channel which is not environmentally sensitive, and that the project will not result in the expansion of the existing use of this facility; and
c) Approve Phase 1 and Phase 2 plans for the project.
|