File #: 12-00571    Version: 1
Type: Agenda Item Status: Passed
File created: In control: BOARD OF SUPERVISORS
On agenda: 7/10/2012 Final action: 7/10/2012
Title: Acting as the Board of Directors, Flood Control and Water Conservation District: Consider recommendations regarding the Lillingston Canyon Debris Basin Modification Project Phase 2, First District, as follows: a) Approve the award of a Construction Contract for the Lillingston Canyon Debris Basin Modification Project Phase 2 in the amount of $157,147.50 to the lowest responsible bidder, AIS Construction Company (a local vendor), subject to the provisions of documents and certifications, as set forth in the plans and specification applicable to the project and as required by law; b) Approve and authorize the Chair to execute a Construction Contract upon return of the contractor’s executed contract documents, and the review and approval of County Counsel, Auditor-Controller, and Risk Manager or their authorized representatives; c) Approve a contingency in the amount of $15,714.75 for the above subject construction contract; d) Approve plans and specifications for Lillingston Canyon ...
Sponsors: PUBLIC WORKS DEPARTMENT, BOARD OF DIRECTORS, FLOOD CONTROL AND WATER CONSER
Attachments: 1. Board Letter, 2. Agreement
Title
 
Acting as the Board of Directors, Flood Control and Water Conservation District:
 
Consider recommendations regarding the Lillingston Canyon Debris Basin Modification Project Phase 2, First District, as follows:
 
a) Approve the award of a Construction Contract for the Lillingston Canyon Debris Basin Modification Project Phase 2 in the amount of $157,147.50 to the lowest responsible bidder, AIS Construction Company (a local vendor), subject to the provisions of documents and certifications, as set forth in the plans and specification applicable to the project and as required by law;
 
b) Approve and authorize the Chair to execute a Construction Contract upon return of the contractor's executed contract documents, and the review and approval of County Counsel, Auditor-Controller, and Risk Manager or their authorized representatives;
 
c) Approve a contingency in the amount of $15,714.75 for the above subject construction contract;
 
d) Approve plans and specifications for Lillingston Canyon Debris Basin Modification Project Phase 2; and
 
e) Find that pursuant to the California Environmental Quality Act (CEQA) 14 CCR, Section 15162, no new effects will occur and no new mitigation measures would be required as a result of the project and therefore pursuant to CEQA Section 15168 (2) Program EIR, that the Lillingston Canyon Debris Basin Project is within the scope of the project covered by the Program Environmental Impact Report (PEIR) for the Updated Routine Maintenance Program (01-EIR-01), Findings, and Statement of Overriding Considerations approved in December, 2001, and the Lillingston Debris Basin addendum to the PEIR approved June 15, 2010, and no new environmental document is required.