Title: Acting as the Board of Directors, Flood Control and Water Conservation District: Consider recommendations regarding the Las Vegas and San Pedro Creeks Capacity Improvement Project, Second District, as follows: a) Approve the Transition Structure plans and specifications for the Las Vegas and San Pedro Creeks Capacity Improvement Project; b) Award the construction contract for the Transition Structure portion of the Las Vegas and San Pedro Creeks Capacity Improvement Project, in the amount of $689,528.70 to the lowest responsible bidder Souza Construction, Inc. (not a local vendor), subject to the provisions of documents and certifications, as set forth in the plans and specifications applicable to the project and as required by law; c) Approve and authorize the Chair to execute the construction contract upon return of the contractor's executed contract documents, and the review and approval of the County Counsel, Auditor-Controller, and Risk Manager or their authori...
Sponsors: PUBLIC WORKS DEPARTMENT, BOARD OF DIRECTORS, FLOOD CONTROL AND WATER CONSER
Attachments: 1. Board Letter, 2. Attachment A - Plans and Specifications, 3. Attachment B - Copy of Construction Agreenebt with Souza Construction, 4. Attachment C - Agreement with Filippin Engineering with Contract Summary, 5. Attachment D - Temporary Entry Permit, 6. Attachment E - Permanent Easement
Title

Acting as the Board of Directors, Flood Control and Water Conservation District:

Consider recommendations regarding the Las Vegas and San Pedro Creeks Capacity Improvement Project, Second District, as follows:

a) Approve the Transition Structure plans and specifications for the Las Vegas and San Pedro Creeks Capacity Improvement Project;




b) Award the construction contract for the Transition Structure portion of the Las Vegas and San Pedro Creeks Capacity Improvement Project, in the amount of $689,528.70 to the lowest responsible bidder Souza Construction, Inc. (not a local vendor), subject to the provisions of documents and certifications, as set forth in the plans and specifications applicable to the project and as required by law;

c) Approve and authorize the Chair to execute the construction contract upon return of the contractor's executed contract documents, and the review and approval of the County Counsel, Auditor-Controller, and Risk Manager or their authorized representatives;

d) Authorize the Public Works Director or designee to approve changes or additions to the work being performed under the Construction Contract, in an amount not to exceed $46,976.44 for the Transition Structure portion of the Las Vegas and San Pedro Creeks Capacity Improvement Project;

e) Approve and authorize the Chair to execute the Agreement for Services of Independent Contractor with Filippin Engineering (a local vendor), to provide construction management and inspection services for the Transition Structure portion of the Las Vegas and San Pedro Creeks Capacity Improvement Project for the period of May 3, 2016 through January 31, 2017 in an amount not to exceed $104,384.00;

f) Authorize the Public Works Director or designee to approve changes or additions to the work being performed under the Agreement for Services of Independent Contractor with Filippin Engineering in an amount not to exceed $10,438.40;

g) Approve and authorize the ...